Phase I: Prospect & Preliminary Title
≈ months 0–6 · before leases are signed1 · Prospect Generation
Geologists and engineers identify target acreage: formation depth and thickness, offset well production, existing spacing, and midstream access. The land department gets a map and is told to find out who owns the minerals and lease them.
2 · Runsheets & Mineral Ownership Reports
Landmen search the county records, running the grantor/grantee indexes forward from the patent or other original grant. Each conveyance goes on a runsheet, and ownership is calculated into a mineral ownership report or limited title report. Leasing relies on this report. The attorney's opinion comes later.
Phase II: Leasing & Unit Formation
overlaps Phase I3 · Lease Negotiation & Execution
The parties negotiate bonus per net mineral acre, royalty (commonly 1/8 to 1/4), primary term (often 3 years, sometimes with an option to extend), shut-in terms, Pugh clauses, and depth limits. The signed oil and gas lease (or a memorandum of it) is recorded and becomes part of the chain of title.
4 · Spacing & Pooling
A drilling and spacing unit is established (or an existing one relied on), and the interests inside it are pooled, either by agreement or, where state law allows, by a compulsory (forced) pooling order covering owners who have not agreed. How pooling works varies widely by state.
Phase III: Title Assurance
the first of the two title opinions5 · Drilling Title Opinion (DTO)
Before the operator commits to drilling, a title attorney examines the abstract or runsheet materials and renders the DTO. It states ownership of the minerals and leasehold, addresses the operator's right to drill, and lists requirements: the defects to cure. This is the first of two opinions. It supports the decision to drill; a later opinion supports payment.
6 · Curative
The landman works the DTO requirements with affidavits of heirship, probates or heirship determinations, releases of expired leases and old liens, ratifications, stipulations of interest, and corrective deeds. Some requirements are cured before drilling. Others are waived for drilling and deferred to the division order stage, which is one reason there are two opinions.
Phase IV: Permitting
can be the longest phase · runs parallel to title work7 · Siting & Location Review
Many states require some form of location or siting review before or alongside the drilling permit: setbacks from homes and water, surface owner notice, environmental and wildlife considerations, local government input, and in some states public comment or a hearing. The review ranges from a formality in some states to a process of a year or more in others.
8 · Drilling Permit Approved
Each wellbore needs a permit to drill from the state regulator. Wells on federal or Indian minerals also need a federal Application for Permit to Drill (APD) approved by the BLM. Approval starts a clock: a permit expires if drilling doesn't start in time, often within two years, depending on the state and agency. Operators often hold approved permits for wells they will drill later, when a rig and capital are available and prices justify it.
Phase V: Drilling
heavy spending begins9 · Pad Construction & Rig Move
The operator builds access roads, the pad, cellar, and conductor, and stages surface equipment. Surface use agreements, bonding or financial assurance, and pre-drilling conditions of approval are handled. Then the rig moves in.
10 · SPUD
Drilling starts and the well is spudded. The spud date can matter legally. Depending on the lease, it may satisfy a clause that keeps the lease alive if operations begin before the primary term ends. It can also meet the permit deadline and deadlines in a pooling order. A modern horizontal well commonly reaches total depth in one to four weeks.
11 · TD, Logging, Casing & Cement
The well reaches total depth, is logged and evaluated, and production casing is run and cemented. The rig moves off and the well waits for completion, sometimes briefly, sometimes for months until a frac crew is available. A well in this state is a DUC (drilled but uncompleted).
Phase VI: Completion & First Production
the dates many later deadlines run from12 · Frac, Flowback, Turn-in-Line
The well is fractured, flowed back, hooked up to facilities, and turned to sales, and a completion report is filed. Two dates matter here. First production: if the well is producing when a lease's primary term ends, the lease continues into its secondary term, subject to the lease and state law. First sales: starts the payment clock in Phase VIII.
Phase VII: Production & Accounting
monthly reporting for the life of the well13 · Measurement, Marketing & Reporting
Oil and gas are measured, marketed, and sold; production is reported to the state monthly (and becomes public record in most states, usually on a lag). Severance and ad valorem taxes accrue. Before revenue accounting can pay anyone, it needs each owner's decimal interest.
Phase VIII: Division of Interest & Payment
the second title opinion14 · Division Order Title Opinion (DOTO)
This is the second opinion. The attorney brings title forward to about first sales, covering every mineral owner, royalty owner, NPRI, ORRI, and working interest owner, and renders an opinion on each owner's decimal interest in production from the unit. Requirements waived for drilling are usually taken up again here.
15 · Division Orders Issued
Revenue accounting builds the pay deck from the DOTO and mails division orders asking each owner to confirm their decimal and payment details. A division order generally confirms the decimal and is not meant to change the lease; its exact effect varies by state. Owners with unresolved title defects stay in suspense until cured.
16 · First Royalty Check
Most producing states have a proceeds-payment ("prompt pay") statute that sets a deadline for the first payment after first sale and a schedule after that, often with interest on late payments. The deadlines vary by state. Two to five years after a landman first searched the county records, the owner receives the first royalty check.
Summary
Title work happens at both ends of the project: runsheets, leases and the DTO at the start; the DOTO, division orders and payment at the end. Permitting and operations fall in between. The five topics cover the title side in more detail.